Crossover No. 1,2,3,4 of Sai Gon -Trung Luong Super Highway Project

MONday - 28/05/2012 16:49
Crossover No. 1,2,3,4 of Sai Gon -Trung Luong Super Highway Project

Crossover No. 1,2,3,4 of Sai Gon -Trung Luong Super Highway Project

+ Scale and technical characteristics of the works: the bridge has 6 spans under the circuit 2x30m + 2x25m + 2x30m. Total length: 190,9m. C40 Prestressed reinforced  concrete box beam with depth: 1.45m.  C25 precast reinforced concrete slabs parapet. Abutments in barrier wall shape poured-in-place with body, base, wall, head by C35 reinforced concrete. The foundation by C30 reinforced concrete bored cast-in-place piles.

+ Works value:  83.632 billion VND

+Year of commencement: 2006

+Year of  completion: 2008

+ Employer/ Representative Employer: My Thuan Project Management Unit. Address: No.127 Dinh Tien Hoang, Ward 3, Binh Thanh District, Ho Chi Minh City

 